|
ONLY FOR SUMNER APPLICATORS! |
|
|
|
|
|
|
|
Exterior |
|
|
| |
|
|
|
|
|
|
|
|
|
9.2.1 Installation Checklist for SUMNER trained stone installer
|
|
|
|
|
|
|
|
YES √ |
No √ |
Re Checked YES √ |
Re Checked No √ |
Project:
|
(Basic Description. Columns, chimney etc) |
Manual:
|
Revision: 18th November 2017
|
|
|
| 1.0 Substrate & Pre Installation. |
|
| 1.1 |
Attached Builders 9.1.1 SUMNER Cavity Checklist to the back of this form. |
| 1.2 |
Has 9.1.1 SUMNER Cavity Checklist been completed satisfactory? (If checklist is unavailable you must inspect for correct fitment.) |
|
|
|
|
|
|
- if not then advise the builder and have rectifications made. |
|
|
|
|
|
|
- if builder declines then advise SUMNER office and they will send a Non Compliance letter to the client. Do not commence work! |
|
|
|
|
|
| 1.3 |
Have you examined the areas to be weathertight and advised the main contractor / architect of any existing conditions or surface contaminants which will require correction before work commences. |
|
|
|
|
|
| 1.4 |
The four corners of every window, and the sills have been SUMNER taped? |
|
|
|
|
|
| 1.5 |
Walls are vertical and plumb (not leaning out) |
|
|
|
|
|
| 1.6 |
Have you been asked to clad any ceiling or inverted areas? |
|
|
|
|
|
| 1.7 |
Ensure SUMNER Cavity System is NOT installer over non-structural brick, steel frame, aerated concrete or another veneer/cavity? |
|
|
|
|
|
| 1.8 |
Have you verified with your moisture meter that timber framing has a moisture content <18% BEFORE installing stonework? |
|
|
|
|
|
| 1.9 |
Any horizontal surfaces have a 10 degrees slope |
|
|
|
|
|
| 2.0 Licence Info |
|
|
|
|
| 2.1 |
Have you completed a SUMNER Installer training day? |
|
|
|
|
|
| 2.2 |
Are you a Licensed Building Practitioner |
Write LBP No: |
_ _ _ _ _ _ _ _ _ _ |
|
|
|
|
|
|
|
| 3.0 SUMNER Taping |
|
|
|
|
| 3.0 |
Have you inspected to see you are not installing over another coating/seal? |
|
|
|
|
|
| 3.1 |
When installing the tape over SUMNER Sheeting, did it cover 100% of all joins, voids and gaps? |
|
|
|
|
|
| 3.2 |
Was surface temperature between 10 and 32 degrees Celsius? |
|
|
|
|
|
| 3.3 |
Primer & Joins: Did you apply SUMNER Prime to board surface, and then tape the joints? |
|
|
|
|
|
| 3.4 |
Try tearing a small thumb nail of the tape away. It should not come away easily. Tick yes if this test was carried out. |
|
|
|
|
|
3.5
|
Tape perimeter of all penetrations (doors,windos,pipes,meterboxes)
|
|
|
|
|
|
| 4.0 Installation |
|
|
|
|
|
|
| 4.1 |
Was the back of the stone free of excessive water which inhibits the adhesive bond? |
|
|
|
|
|
| 4.2 |
Were SUMNER adhesives used and mixed as per specification? |
|
|
|
|
|
| 4.3 |
Were adequate props used along the bottom prior to install? |
|
|
|
|
|
| 4.4 |
Was both the board and stone free from dirt, dust or contaminants? |
|
|
|
|
|
|
CONTROL JOINTS |
|
|
|
|
|
| 4.5 |
Cumulative Lineal Expansion: Where any walls more than 8 meters high, or longer than 5 meters wide? |
|
|
|
|
|
| 4.6 |
Substrate Expansion Joins: Are there any mid floor expansion joints? |
|
|
|
|
|
| 4.7 |
If yes to either of the above, tick how control joints were accommodated into the stone Installation. |
Slip-joint |
Cut expansion joint into the panel wall. |
loose stone with room for expansion |
| 4.8 |
Was installed stone protected from weather until cured (2 days)? |
|
|
|
|
|
| 4.9 |
Were SUMNER fixings installed at minimum 600mm vertical centres horizontal centres. |
|
|
|
|
|
| 4.10 |
Did you avoid rehydrating or using an adhesive mix older than 1 hour? |
|
|
|
|
|
| 4.11 |
Did you ensure stone was not soaking wet on the back when you were troweling the adhesive? |
|
|
|
|
|
| 4.12 |
Was adhesive troweled on the stone, and a thin skim coat to the wall to ensure the adhesive was taking to both surfaces? |
|
|
|
|
|
| 5.0 Other Important Checks |
|
|
|
|
|
|
| 5.1 |
The temperature was not under 10 or over 32 degrees when adhering the stone? |
|
|
|
|
|
| 5.2 |
Were panels spot fixed? |
|
|
|
|
|
| 5.3 |
95% coverage troweled on the back of the stone, and thick enough with a 10mm notched trowel to effect the same percentage bond to the substrate? |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 7.0 Stone Slip used |
|
|
|
|
|
|
| 7.1 |
Nominate type: Ledgestone, Traditional or Sandstone Series □ |
|
|
|
|
|
|
Otago or Bluestone Series □ |
|
|
|
|
|
|
|
|
|
|
|
|
| NAME OF APPLICATOR: |
|
|
|
|
| SIGN HERE |
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ |
Date: |
|
|
|
|
|
Note: This form is a legal document and you will be held liable for the costs of any failures, whether direct or indirect, due to falsifications in the document. |
|
|
|
|
|
| REQUEST SUMNER OFFICE FOR PRODUCER STATEMENT AND WARRANTY. |
| Site Address:- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Consent No:- |
|
|
|
|
|
|
| Territorial |
|
|
|
|
|
|
| Authority:- |
|
|
|
|
|
|
| Fixer/ Builder |
|
|
|
|
|
|
| Contact Details:- |
|
|
|
|
|
|
| Phone:- |
|
|
|
|
|
|
| Mobile:- |
|
|
|
|
|
|
| E-mail:- |
|
|
|
|
|
|
| Please note all Producer Statement requests must be completed and signed |
|
|
|
|
|
|
| by a SUMNER applicator. |
|
|
|
|
|
|
|
|
Date: |
|
|
|
|
|
This document is the copyright of SUMNER 2005 |
|
|
|
|
|